Contingency Logistics
Rapid Construction of Temporary Camp
CRC designed and stood up a full-service camp in Obo, CAR within a tight 60-day deployment and construction timeline.
Client: DOD
CRC designed a full-service camp in Obo, CAR within a 60-day deployment and construction timeline that included addressing requirements for disassembly and remediation within one week’s time, per customer requirements. In response to last minute changes, CRC was required to have the camp mobilized, ready to occupy, and operational within 14 days of Notice to Proceed from the customer.
